Pennsylvania Ave Update 8/13/11

IMG_0293
IMG_0292
IMG_0285

At top: Pennsylvania Avenue panorama looking north
In the middle: looking south
At Bottom: Another look at the rock wall 

An agenda item for the 8/15/11 City Council meeting will be a contract modification for the rock excavation on Pennsylvania Ave. 

Additional rock was encountered during the excavation of the sanitary sewer as well as during the excavation of the east retaining wall.  The anticipated rock excavation: 100 cubic yards; the actual amount removed: 685 cubic yards. 

Although the price of excavating the rock will rise (by $94K), the rock along the east face may allow the reduction of the retaining wall by half, which may reduce the contract by approximately $35K. 

More information is at the City Council Packet Memo, which you can view here